RECENT PROJECTS
Project values are divided into the two following categories
Category 1 Large renovation/upgrade with values greater than 3 million
Category 2 Middle to small range renovation/upgrade projects with values less than 3 million
 |
Project Name |
Four Seasons Hotel |
| Location |
Downtown Vancouver, BC |
| Rooms |
389 |
| Value |
Category 1 |
| Duration |
7 months + ongoing. |
| Project Scope |
Complete interior upgrade, including guest rooms, guest hallways and
meeting rooms. |
| Unique Feature |
Level 5 finish to all texture ceilings. On time hand over of every floor, one each Friday at 4PM. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Delta Vancouver Airport Hotel |
| Location |
Richmond, BC |
| Rooms |
420 |
| Value |
Category 1 |
| Duration |
8 months |
| Project Scope |
Complete interior upgrade, including all guest rooms, guest hallways, Ballrooms, washrooms and lobbies etc. Finishing & structural changes, plumbing, electric, tiling, carpentry etc. |
| Unique Experience |
Meeting the demands of an extremely tight Pre-Olympic schedule, working closely with owners, management and designers to meet the requirements of budget & schedule. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Sheraton Wall Center |
| Location |
Downtown Vancouver, BC |
| Rooms |
260 |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Refinish walls, doors, ceilings and millwork. |
| Unique Challenge |
Extremely tight schedule during the Christmas season. Completed two
days ahead of schedule. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Holiday Inn |
| Location |
Downtown Vancouver, BC |
| Rooms |
240 + |
| Value |
Category 2 |
| Duration |
On-going |
| Project Scope |
Interior upgrade, including guestrooms, guest hallways, conference rooms and lobbies etc. |
| Unique Program |
Project spread out to meet unique budget requirement. On time each phase. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Sutton Place Hotel |
| Location |
Downtown Vancouver, BC |
| Rooms |
360 |
| Value |
Category 2 |
| Duration |
6 month |
| Project Scope |
Refinishing of guest rooms, guest hallways and swimming pool area, walls, doors, ceilings, millwork. On time handover on every floor. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Vancouver Central Library |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
2 months |
| Project Scope |
Exterior power washing, hand cleaning and sealing. Interior refinishing. |
| Unique Challenge |
Working alongside many operating business & heavy pedestrian traffic. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Cascadia Hotel & Suites |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Remove and reinstall ceilings after major HVAC upgrade. Assorted additional scopes of work; ongoing. |
| Unique Challenge |
Driving schedule to complete work including HVAC trades while floors
were open. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Plaza 500 Hotel |
| Location |
West 12th & Cambie, Vancouver, BC |
| Value |
Category 2 |
| Duration |
3 months |
| Project Scope |
Exterior concrete restoration, cleaning, sealing & painting with window refinishing. |
| Unique Challenge |
Hotel had to remain open during work. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Westin Bayshore Hotel |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Interior common area painting finishing. |
| Unique Needs |
Hotel had to remain open during work. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Empire Landmark Hotel |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Repainting of the revolving restaurant’s interior including bus stations, bars etc. |
| Unique Demands |
Hotel had to open restaurant for breakfast, and reopen for dinner each day. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Quality Hotel |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
2 months |
| Project Scope |
Exterior painting and restoration work as well as interior paint finishing. |
| Unique Challenge |
Working within the schedule of an operating hotel. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Marriott Pinnacle Hotel |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Exterior stucco restoration work. |
| Unique Feature |
To blend in the stucco work so the restoration work is indistinguishable from the original, at front entry while guests continued to arrive undisturbed. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Executive Hotel |
| Location |
Richmond, BC |
| Value |
Category 2 |
| Duration |
1 month |
| Project Scope |
Interior painting finishes. |
| Unique Feature |
Working within the schedule of an operating hotel. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Opus Hotel |
| Location |
Downtown Vancouver, BC |
| Value |
Category 2 |
| Project Scope |
Exterior water proofing. |
| Unique Feature |
Working within the schedule of an operating hotel. |
|
VIEW PHOTO GALLERY |
 |
Project Name |
Jamieson Court |
| Location |
New Westminster, BC |
| Value |
Category 2 |
| Duration |
4 months |
| Project Scope |
Exterior water proofing. |
| Unique Feature |
All interior common areas upgrade, walls, floor, ceilings etc. |
|
VIEW PHOTO GALLERY |